ARTICLE · 21 SEPTEMBER 2018

FERC Grants Partial Rehearing Of PJM Uplift Allocation Order

On September 6, 2018, FERC denied the PJM Interconnection, L.L.C.'s ("PJM") rehearing request of FERC's prior order rejecting proposed revisions to PJM's Amended and Restated Operating Agreement

United StatesEnergy and Natural Resources

On September 6, 2018, FERC denied the PJM Interconnection, L.L.C.'s ("PJM") rehearing request of FERC's prior order rejecting proposed revisions to PJM's Amended and Restated Operating Agreement ("Operating Agreement") and Open Access Transmission Tariff ("OATT") that would allocate uplift charges to Up-to-Congest transactions ("UTCs") similarly to other virtual transactions.  However, FERC granted rehearing in part to accept PJM's proposal to exclude internal bilateral transactions from the calculation of supply and demand deviations for the purpose of uplift allocation.

In October 2017, PJM proposed to allocate uplift charges to UTCs (i.e., a type of virtual transaction) in the same way that uplift is allocated to other virtual transactions — namely, incremental offers of supply ("INCs") and decrement demand bids ("DECs").  In an order dated January 12, 2018 ("January 12 Order"), FERC rejected PJM's proposal, without prejudice, on the grounds that PJM had failed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from