On September 20, 2018, FERC dismissed Nevada Hydro Company,
Inc.'s ("Nevada Hydro") request that (1) the Lake
Elsinore Advanced Pumped Storage ("LEAPS") facility is a
transmission facility and (2) LEAPS is entitled to cost-based rate
recovery under the California Independent System Operator
Corporation's ("CAISO") Transmission Access
Charge. FERC found that Nevada Hydro's request is
premature because LEAPS has not been studied in the CAISO
Transmission Planning Process ("TPP") to determine
whether it addresses a transmission need identified through that
process, and, if such a need were met, how the facility would be
operated.
Nevada Hydro's proposed $2 billion LEAPS project consists of
two primary components: (1) a 500 MW pumped storage facility to be
located on Lake Elsinore in Riverside, California; and (2) the
Talega-Escondido/Valley-Serrano 500 kV Interconnect, a 30-mile
transmission line that will interconnect the pumped storage
facility to the transmission