ARTICLE · 09 DECEMBER 2015

FERC Finds No Significant Additive Or Cumulative Impacts From Tennessee's Northeast Upgrade Project On Remand

On November 19, 2015, FERC issued an order on remand from the U.S. Court of Appeals for the D.C. Circuit finding that, when considered with the other projects involving construction on the 300 Line pipeline, Tennessee Gas Pipeline, L.L.C.'s Northeast Upgrade Project does not result in significant additive or cumulative impacts.

United StatesEnergy and Natural Resources

On November 19, 2015, FERC issued an order on remand from the U.S. Court of Appeals for the D.C. Circuit ("D.C. Circuit") finding that, when considered with the other projects involving construction on the 300 Line pipeline, Tennessee Gas Pipeline, L.L.C.'s ("Tennessee") Northeast Upgrade Project does not result in significant additive or cumulative impacts. FERC originally held that it did not segment its environmental review of the Northeast Upgrade Project from that of the 300 Line Project and that its cumulative impacts analysis was not deficient. However, the D.C. Circuit remanded the additive and cumulative impacts analysis to FERC for further consideration.

On March 31, 2011, Tennessee filed an application requesting authorization to construct and operate the Northeast Upgrade Project, which consists of five pipeline loop segments totaling 40.3 miles of 30-inch-diameter pipeline, modifications and upgrades at four compressor stations, and one meter station.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.