FERC Denies Wisconsin Power And Light’s Request For Waiver Of MISO Tariff Provisions

On March 24, 2015, the Commission denied Wisconsin Power and Light Company's ("WPL") request for waiver of certain provisions of the Midcontinent Independent System Operator's Open Access Transmission...

United StatesEnergy and Natural Resources

On March 24, 2015, the Commission denied Wisconsin Power and Light Company's ("WPL") request for waiver of certain provisions of the Midcontinent Independent System Operator's ("MISO") Open Access Transmission, Energy and Operating Reserve Markets Tariff (the "MISO Tariff") dealing with annual capacity obligations.  Despite denying WPL's request, the Commission noted that it was concurrently issuing a separate order to modify the MISO Tariff which would, according to the Commission, provide WPL with the relief it sought.

On January 16, 2015, WPL requested waiver of: (1) the "must-offer" requirement that accompanies capacity obligations; and (2) the requirement to purchase replacement capacity for units that do not meet their capacity obligations.  The waiver was requested in response to what WPL referred to as a "compliance dilemma."  Pursuant to a 2013 consent agreement entered into with the EPA to resolve alleged violations of the Clean Air Act, WPL had agreed to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from