On September 20, 2018, FERC denied rehearing and partially
granted clarification of its order regarding Multi-Value Project
("MVP") rate pancaking charges between PJM
Interconnection, L.L.C. ("PJM") and the Midwest
Independent Transmission System Operator, Inc. ("MISO").
In the underlying order, FERC determined that because MISO's
transmission projects benefited the existing MISO-PJM system, the
limitation on rate pancaking imposed by FERC in 2003 and 2010 was
no longer reasonable.
Dating back to July 2002, FERC permitted various utilities to
join PJM instead of MISO. At the time, FERC was concerned that the
inclusion of these utilities would result in an "elongated and
highly irregular seam between MISO and PJM" that would isolate
Wisconsin and Michigan from the rest of MISO—and would,
necessarily, subject numerous transactions to rate pancaking, where
a transmission customer would be charged separate access charges
for each regional transmission organization