FERC Denies Rehearing, Partially Grants Clarification On MVP Rate Pancaking Order

On September 20, 2018, FERC denied rehearing and partially granted clarification of its order regarding Multi-Value Project rate pancaking charges between PJM Interconnection, L.L.C. and the ...

United StatesEnergy and Natural Resources

On September 20, 2018, FERC denied rehearing and partially granted clarification of its order regarding Multi-Value Project ("MVP") rate pancaking charges between PJM Interconnection, L.L.C. ("PJM") and the Midwest Independent Transmission System Operator, Inc. ("MISO"). In the underlying order, FERC determined that because MISO's transmission projects benefited the existing MISO-PJM system, the limitation on rate pancaking imposed by FERC in 2003 and 2010 was no longer reasonable.

Dating back to July 2002, FERC permitted various utilities to join PJM instead of MISO. At the time, FERC was concerned that the inclusion of these utilities would result in an "elongated and highly irregular seam between MISO and PJM" that would isolate Wisconsin and Michigan from the rest of MISO—and would, necessarily, subject numerous transactions to rate pancaking, where a transmission customer would be charged separate access charges for each regional transmission organization

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from