On September 20, 2018, FERC denied the Utah Board of Water
Resources ("Utah Board") and the Washington County Water
Conservancy District's petition for a declaratory order, asking
FERC to find that its licensing jurisdiction under the Federal
Power Act ("FPA") extends to all of the Lake Powell
Pipeline Project facilities identified in the Board's license
application for the project, including 89 miles of water delivery
pipeline.
On May 2, 2016, the Utah Board filed an application with FERC
for its proposed Lake Powell Project, which would transport up to
100,000 acre-feet of water annually from Lake Powell in
northwestern Arizona through a buried 69-inch-diameter pipeline to
southern Utah, where the water would be pumped approximately 50
miles to a high point within the Grand Staircase-Escalante National
Monument, from which it would flow downhill 89 miles, passing
through four in-line hydroelectric turbines, a 35-megawatt
("MW") peaking project at Hurricane Cliffs,