ARTICLE · 30 MAY 2018

FERC Denies NJBPU Complaint Regarding Bergen-Linden Corridor Project In PJM

On May 24, 2018, FERC denied a complaint filed by the New Jersey Board of Public Utilities ("NJBPU") alleging unjust and unreasonable cost allocations for the Bergen-Linden Corridor transmission project...

United StatesEnergy and Natural Resources

On May 24, 2018, FERC denied a complaint filed by the New Jersey Board of Public Utilities ("NJBPU") alleging unjust and unreasonable cost allocations for the Bergen-Linden Corridor transmission project (the "Project") within the PJM Interconnection, L.L.C. ("PJM") footprint.  FERC rejected NJBPU's claims that, among other alleged problems, PJM's implementation of certain provisions in its tariff and the Joint Operating Agreement (the "JOA") with the New York Independent System Operator, Inc. ("NYISO") unfairly insulated New York ratepayers from costs associated with the Project, at the expense of New Jersey ratepayers and in violation of FERC's Order No. 1000.  

To help address short circuit issues in New Jersey, PJM selected the Project in 2013 through its Regional Transmission Expansion Planning process.  Several years later, in 2017, Consolidated Edison Company of New York, Inc. ("ConEd") terminated various transmission service agreements that had allowed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from