FERC Denies Complaint For Identical Treatment Of Demand Response Resources And Generation Resources In PJM's Capacity Market

The Market Monitor filed its complaint under section 206 of the Federal Power Act ("FPA") on January 27, 2014.

United StatesEnergy and Natural Resources

On April 21, 2016, the Federal Energy Regulatory Commission ("FERC") denied a complaint from Monitoring Analytics, LLC, the independent market monitor ("Market Monitor") for PJM Interconnection, L.L.C. ("PJM"), alleging that PJM's existing capacity market rules fail to treat demand response resources in a manner comparable to generation capacity resources. Specifically, the Market Monitor asserted that demand response resources should be subject to: (i) a must-offer requirement, as applicable to PJM's day-ahead energy market; and (ii) an offer cap on all energy offers, as applicable to generation resources.

The Market Monitor filed its complaint under section 206 of the Federal Power Act ("FPA") on January 27, 2014. In the complaint, the Market Monitor requested that FERC order PJM to treat demand response as an economic resource required to offer into the day-ahead energy market, subject to the offer cap that currently applies to generation resources. In support of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from