ARTICLE · 23 JULY 2018

Ferc Denies Application To Terminate PURPA Mandatory Purchase Obligation

On July 9, 2018, FERC denied Cloverland Electric Cooperative's ("Cloverland") application to terminate its mandatory obligation under the Public Utilities Regulatory Policies Act of 1978 ("PURPA") ...

United StatesEnergy and Natural Resources

On July 9, 2018, FERC denied Cloverland Electric Cooperative's ("Cloverland") application to terminate its mandatory obligation under the Public Utilities Regulatory Policies Act of 1978 ("PURPA") to purchase electric energy and capacity from qualifying cogeneration or small power production facilities ("QF") with a net capacity in excess of 20 megawatts. In denying the request, FERC emphasized that direct membership in regional transmission organizations or independent system operators is necessary to meet the exemption Cloverland requested under PURPA.

Within the PURPA framework, an electric utility may be relieved of its obligation to purchase QF output if it satisfies certain requirements. For QFs larger than 20 MW, FERC will allow the termination of the requirement to purchase the QF output if FERC finds that the QF has nondiscriminatory access to competitive or independently administered markets, whereby it can meaningfully participate and sell its capacity and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from