FERC Declines To Require Removal Of The Security Requirement For Transmission Owning Interconnection Customers Under The MISO Pro Forma GIA

On September 9, 2016, FERC conditionally accepted an unexecuted Generator Interconnection Agreement ("GIA") filed by the Midcontinent Independent System Operator, Inc.

United StatesEnergy and Natural Resources

On September 9, 2016, FERC conditionally accepted an unexecuted Generator Interconnection Agreement ("GIA") filed by the Midcontinent Independent System Operator, Inc. ("MISO" or the "ISO") involving Duke Energy Indiana, LLC ("Duke Indiana") as the interconnection customer, Duke Energy Business Services, LLC, on behalf of Duke Indiana, as the transmission owner, and MISO as the transmission provider. In so doing, FERC declined a request from Duke Indiana to require MISO to amend its pro forma GIA to address potential future situations in which an integrated utility acts as both the transmission owner and interconnection customer.

MISO submitted the unexecuted GIA on July 11, 2016 and noted the parties' disagreement over two milestones giving effect to pro forma GIA Articles 11.5 and 11.6. Under those provisions, MISO noted, the interconnection customer must either initially pay 20% of all "Network Upgrades and Transmission Owner Interconnection Facilities," or 100

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from