FERC Declares That Proposed Wind Curtailment Violates PURPA

The FERC ruled in September that Idaho Power Company’s proposed curtailment policy for purchases from qualifying facilities violates the Public Utility Regulatory Policies Act of 1978.

United StatesEnergy and Natural Resources

The Federal Energy Regulatory Commission (FERC) ruled in September that Idaho Power Company's (Idaho Power) proposed curtailment policy for purchases from qualifying facilities (QF) violates the Public Utility Regulatory Policies Act of 1978 (PURPA) because it allows the utility to curtail its wind power purchases under previously negotiated power purchase agreements when demand is low.

The Idaho Public Utilities Commission (PUC) had directed Idaho Power to lodge with the PUC a new curtailment policy allowing Idaho Power to halt purchases from QFs that it was otherwise contractually obligated to make when demand for power was low, such as during off-peak periods.  The state proceeding is ongoing.  In response to the filed proposal, Idaho Wind Partners 1, LLC (Idaho Wind) petitioned FERC for an order declaring the new policy to violate section 210 of PURPA.  Certain FERC regulations that implement PURPA require electric utilities to purchase energy and capacity made

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from