On November 19, 2015, FERC issued an order confirming that
certain qualifying facilities ("QFs") under the Public
Utility Regulatory Policies Act of 1978 ("PURPA") with
market-based rate ("MBR") authority, generator
interconnection facilities, or other jurisdictional assets are
exempt from section 203(a)(1) of the Federal Power Act
("FPA"), which requires public utilities to receive
Commission authorization before acquiring or disposing of certain
jurisdictional facilities.
FERC's order arose out of a request for a declaratory order
filed by Chevron U.S.A. Inc. ("Chevron"). In its
request, Chevron sought a determination that sections 210 of PURPA,
and 292.601(c) of FERC's regulations, exempted Chevron's QF
affiliates with MBR authorization from section 203(a)(1) of the
FPA. Certain small power production QFs have long been
exempted from Section 203, but the recent trend of QFs seeking
market-based rate authority to make non-QF sales brought that
exemption into