ARTICLE · 17 MARCH 2016

FERC Conditionally Approves Ten Categories Of Revisions To CAISO Generator Interconnection Process

The proposed amendments represent the second and final set of OATT revisions resulting from CAISO's 2015 interconnection enhancement stakeholder initiative.

United StatesEnergy and Natural Resources

On March 7, 2016, the Federal Energy Regulatory Commission ("FERC" or the "Commission") conditionally approved amendments to the California Independent System Operator Corporation's ("CAISO") Open Access Transmission Tariff ("OATT") that are designed to enhance CAISO's generator interconnection process. The proposed amendments represent the second and final set of OATT revisions resulting from CAISO's 2015 interconnection enhancement stakeholder initiative.

In its January 7, 2016 filing, CAISO proposed tariff amendments to its generator interconnection process whereby:

1) CAISO, rather than the interconnection customer, will notify affected third-party systems of proposed generator interconnection requests, and the affected system will have 60 days to verify whether they are actually affected and want to be involved in the interconnection study process;