On February 5, 2018, FERC conditionally accepted a proposal by the PJM Interconnection, L.L.C. ("PJM") to amend its Open Access Transmission Tariff ("OATT") ...

United StatesEnergy and Natural Resources

On February 5, 2018, FERC conditionally accepted a proposal by the PJM Interconnection, L.L.C. ("PJM") to amend its Open Access Transmission Tariff ("OATT") and Amended and Restated Operating Agreement ("Operating Agreement") to accommodate additional pseudo-tied and dynamically scheduled resources into the PJM region. FERC accepted the proposal and provided an effective date of November 9, 2017, provided that PJM submits a compliance filing addressing FERC's limited concerns in the order.

In its proposal, which PJM submitted on August 11, 2017 and amended on December 7, 2017, PJM described its efforts in recent years to incorporate dynamically transferred resources that are physically located outside of its system. As PJM explained, dynamic transfers include dynamic schedules and pseudo-ties — mechanisms whereby, in relevant part, the output of a generator located in an external balancing authority is transferred into PJM and under PJM's operational and dispatch

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from