Two FERC Commissioners are asking electric transmission
providers to introduce “cure periods” into their
interconnection procedures, hoping to reduce the likelihood that
energy projects are thrown back to the start of the development
process by minor interconnection rules infractions.
On February 2, 2024, FERC affirmed an earlier Order that denied
a request for a limited waiver of PJM's tariff by Scioto
Farms Solar Project, LLC (“Scioto Farms”), the
developer of a proposed solar generation facility in Wayne
Township, Ohio. The backstory: as of June 2023, Scioto Farms had
obtained an interconnection agreement with PJM, the regional grid
operator, and AEP Ohio Transmission Co., the local transmission
owner. But due to a clerical error by its guarantor bank, Scioto
Farms' letter of credit (which PJM requires to be filed
within 120 days of signing an interconnection agreement) was
delivered late—a single day past the deadline.