FERC Commissioners Phillips, Clements Call For "Cure Periods" In Interconnection Procedures

Two FERC Commissioners are asking electric transmission providers to introduce "cure periods" into their interconnection procedures, hoping to reduce the likelihood that energy projects...

United StatesEnergy and Natural Resources

Two FERC Commissioners are asking electric transmission providers to introduce “cure periods” into their interconnection procedures, hoping to reduce the likelihood that energy projects are thrown back to the start of the development process by minor interconnection rules infractions.

On February 2, 2024, FERC affirmed an earlier Order that denied a request for a limited waiver of PJM's tariff by Scioto Farms Solar Project, LLC (“Scioto Farms”), the developer of a proposed solar generation facility in Wayne Township, Ohio. The backstory: as of June 2023, Scioto Farms had obtained an interconnection agreement with PJM, the regional grid operator, and AEP Ohio Transmission Co., the local transmission owner. But due to a clerical error by its guarantor bank, Scioto Farms' letter of credit (which PJM requires to be filed within 120 days of signing an interconnection agreement) was delivered late—a single day past the deadline. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from