ARTICLE · 14 OCTOBER 2012

FERC Clarifies That A Utility May Not Curtail Unilaterally For Purchases From QFs Under A Long-Term Obligation

On September 20, FERC granted Idaho Wind Partners 1, LLC’s (Idaho Wind’s) petition for declaratory order concerning an Idaho Power Company (Idaho Power) tariff provision providing for curtailments of energy from qualifying facilities (QFs).

United StatesEnergy and Natural Resources

On September 20, FERC granted Idaho Wind Partners 1, LLC's (Idaho Wind's) petition for declaratory order concerning an Idaho Power Company (Idaho Power) tariff provision providing for curtailments of energy from qualifying facilities (QFs).1 Under that tariff provision, Idaho Power would have been able to curtail purchases from certain QFs if, due to operational circumstances, such purchases would require Idaho Power to dispatch higher cost resources to serve system load or would make Base Load Resources unavailable for serving the next anticipated load.

Idaho Wind sought a ruling that Idaho Power's tariff would violate the Public Utility Regulatory Policies Act of 1978 (PURPA) if Idaho Power curtails purchases from QFs with fixed avoided-cost rate contracts, regardless of whether Idaho Power acts unilaterally or pursuant to a schedule or policy approved by the Idaho Commission.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from