FERC Assesses $1.2 Million Civil Penalty For Abandonment Without Authorization And Incomplete Application

FERC's order and the accompanying Stipulation and Consent Agreement describe two sets of violations.

United StatesEnergy and Natural Resources

A recent Federal Energy Regulatory Commission (FERC) order approving a Stipulation and Consent Agreement between Georgia-Pacific Crossett LLC (GPC) and FERC's Office of Enforcement providing for payment of a $1.2 million civil penalty serves as an important object lesson for all natural gas companies owning interstate natural gas pipelines or other jurisdictional facilities subject to a certificate of public convenience and necessity under Section 7(c) of the Natural Gas Act (NGA).

FERC's order and the accompanying Stipulation and Consent Agreement describe two sets of violations. First, because GPC largely completed abandonment work on its pipeline and related facilities before filing for abandonment authorization, it abandoned a jurisdictional interstate pipeline without prior FERC approval contrary to Section 1(b). Second, GPC's application lacked:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from