FERC Asserts Its Authority To Review Rejection Of Wholesale Power Agreements Days Before PG&E Files Bankruptcy

On Jan. 25, 2019 the FERC issued an order asserting its concurrent authority to approve proposed rejection of wholesale power purchase agreements under the Bankruptcy Code.

United StatesEnergy and Natural Resources

Tara Kaushik and Robert Labate are an attorneys in Holland & Knight's San Francisco office

On Jan. 25, 2019 – just days before  Pacific Gas and Electric (PG&E) proposes to file its bankruptcy case – the Federal Energy Regulatory Commission (FERC) issued an order asserting its concurrent authority to approve proposed rejection of wholesale power purchase agreements under the Bankruptcy Code. The order, issued in NextEra Energy, Inc. v. Pacific Gas and Electric Company, 166 FERC ¶ 61,049 (Docket No. EL 19-35-000),  concludes that FERC and the bankruptcy courts have concurrent jurisdiction to address the disposition of wholesale power contracts that a bankruptcy debtor, like PG&E, seek to reject. The issue is significant, as PG&E is expected to file bankruptcy on or about Jan. 29, 2019. and, in that bankruptcy, is likely to seek court approval for rejecting above-market wholesale power agreements. The order also sets up the potential for regulators of PG&E,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from