On September 7, 2016, FERC accepted the New York Independent
System Operator Inc.'s ("NYISO") proposed revisions
to Attachment Y of its Open Access Transmission Tariff
("OATT") to modify its Public Policy Transmission
Planning Process. Additionally, FERC clarified its requirement that
NYISO establish a cost allocation methodology for the transmission
portion of an "Other Public Policy Project" that is
selected during the regional transmission planning process
consistent with Order No. 1000.
NYISO originally filed the proposed revisions on February 18,
2016. Under NYISO's proposal, an "Other Public Policy
Project" could include "a portfolio of transmission and
non-transmission projects." Nonetheless, according to FERC,
NYISO proposed to treat such mixed use projects as if the entire
portfolio was a non-transmission alternative, making the entire
project ineligible for regional cost allocation. In an April 18
Order, FERC concluded that if an Other Public Policy