ARTICLE · 10 DECEMBER 2016

FERC Approves PSCo Tariff Revisions Regarding Energy And Generator Imbalance Penalty Charges

On November 30, 2016, FERC issued an order accepting tariff revisions filed by Public Service Company of Colorado ("PSCo")..

United StatesEnergy and Natural Resources

On November 30, 2016, FERC issued an order accepting tariff revisions filed by Public Service Company of Colorado ("PSCo") regarding penalty charges for energy imbalance and generator imbalance services under Schedules 4 and 9 of PSCo's open access transmission tariff ("OATT"). FERC found the revisions, which PSCo filed to address the influx of variable wind generation on its system, to provide incentives for accurate scheduling from transmission customers.

As part of the pro forma OATT reforms in Order No. 890, the Commission adopted Schedules 4 and 9 to address energy and generator imbalances, respectively, and to set out penalty charges for such imbalances. In Order No. 890, FERC also considered three principles in crafting the pro forma OATT's imbalance charges. Most relevant here, FERC determined that the penalty charges must be structured to encourage accurate scheduling among transmission customers. Order No. 890 also requires that any transmission provider

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.