ARTICLE · 28 MAY 2015

FERC Approves Novel NOA Amendment To Address Network Upgrades Required Solely To Accommodate QFs Siting In Constrained Areas

In an order issued May 21, 2015, FERC approved an amendment to PacifiCorp's Network Operating Agreement ("NOA") between PacifiCorp and its merchant function, PacifiCorp Energy...

United StatesEnergy and Natural Resources

In an order issued May 21, 2015, FERC approved an amendment to PacifiCorp's Network Operating Agreement ("NOA") between PacifiCorp and its merchant function, PacifiCorp Energy, allowing for a new planning redispatch protocol.  The amendment prevents the need for PacifiCorp to build network upgrades that are driven solely by qualifying facility ("QF") requests to site in a constrained area, and that are not otherwise needed for economic or reliability reasons.

Under the Public Utility Regulatory Policies Act of 1978 ("PURPA"), utilities have a mandatory obligation to purchase QF output, as well as to make firm transmission arrangements to deliver that QF power.  In making its requested NOA amendment, PacifiCorp explained that PacifiCorp Energy has historically designated QF power purchase agreements ("PPA") as network resources in order to provide the requisite firm transmission service.  However, when a QF chooses to site its project in a constrained area, there may

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from