On June 30, 2015, FERC approved most of the proposed tariff
revisions in a joint proposal from the ISO New England, Inc.
("ISO-NE") and the New England Power Pool
("NEPOOL") Participants Committee addressing the
ISO-NE's market monitor rules. Specifically, the proposed
revisions are designed to mitigate the potential to exercise market
power in the ISO-NE Forward Capacity Auction ("FCA"),
which is used to secure capacity in ISO-NE three years in advance
of the relevant delivery year. Going forward, the new rules
approved by FERC will be implemented in ISO-NE's next FCA in
February 2016.
In general, ISO-NE and NEPOOL's proposal contained four
primary revisions: (1) increasing the dynamic "de-list bid
threshold" – the lowest price at which resources are
willing to supply capacity – from $3.94/kW-month to
$5.50/kW-month; (2) limiting the amount, and flexibility, by which
capacity suppliers can modify or withdraw their original static
de-list bids after submission;