ARTICLE · 30 MARCH 2015

FERC Approves Blanket Waiver Of Tariff Requirements For An Interconnection Customer’s Interconnection Facilities

On March 19, 2015, FERC issued Order No. 807, which eliminated Open Access Transmission Tariff ("OATT") requirements, Open Access Same-Time Information System requirements, and the Standards of Conduct requirements, under certain conditions, for the ownership, operation, and control of an Interconnection Customer’s Interconnection Facilities ("ICIF").

United StatesEnergy and Natural Resources

On March 19, 2015, FERC issued Order No. 807, which eliminated Open Access Transmission Tariff ("OATT") requirements, Open Access Same-Time Information System requirements, and the Standards of Conduct requirements, under certain conditions, for the ownership, operation, and control of an Interconnection Customer's Interconnection Facilities ("ICIF").  FERC stated that the waiver is designed to relieve the burden on ICIF owners while still maintaining the rights of third parties to seek access to available ICIF excess capacity.

On May 15, 2014, FERC issued the proposed waiver for ICIF because, according to FERC, "OATT requirements as applied to ICIF may impose risks and burdens on generators and create regulatory inefficiencies that are not necessary to achieve the Commission's open access goals" (see May 16, 2014 edition of the WER).  FERC explained that, under its current rule, ICIF owners were required to make excess capacity available to third parties unless

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from