FERC Affirms Liberalization Of Natural Gas Pipeline Capacity Release Regulations, Provides Clarification

Order 712-A represents FERCs continued effort to liberalize its natural gas policies and regulations.

United StatesEnergy and Natural Resources
Kenneth Irvin
Kenneth Irvin
Gregory Lawrence
Gregory Lawrence
Mustafa Ostrander
Mustafa Ostrander
Author LinkedIn connections

Order 712-A represents FERC's continued effort to liberalize its natural gas policies and regulations.

On November 21, 2008, the Federal Energy Regulatory Commission (FERC) issued an order on addressing several requests for rehearing and clarification of its June 19, 2008, order liberalizing the regulations governing the market for released pipeline and storage capacity. This order continues FERC's efforts to provide additional flexibility to gas market participants.

FERC issued Order 712 in June 2008, in which it adopted several industry proposals to modernize and provide additional flexibility in the market for released capacity (i.e., the sale of gas pipeline/storage capacity from one customer to another). For more information on Order 712, see McDermott's On the Subject entitled "FERC Updates Natural Gas Pipeline Capacity Regulations."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.