FERC Accepts ISO New England's Termination Of Planned Generator's Capacity Supply Obligation

On November 19, 2018, FERC accepted ISO New England Inc.'s ("ISO-NE") request to terminate the capacity supply obligation ("CSO") of the Clear River Unit 1 natural gas-fired generator ("Clear River")

United StatesEnergy and Natural Resources

On November 19, 2018, FERC accepted ISO New England Inc.'s ("ISO-NE") request to terminate the capacity supply obligation ("CSO") of the Clear River Unit 1 natural gas-fired generator ("Clear River") for the 2021–2022 Capacity Commitment Period. In doing so, FERC found that ISO-NE had the right under its Tariff to terminate Clear River's CSO because Clear River's project sponsor, Invenergy Energy Management LLC ("Invenergy"), had covered Clear River's CSO for two consecutive Capacity Commitment Periods. In the same order, FERC denied Invenergy's request for waiver of certain provisions of ISO-NE's Tariff related to the termination of Clear River's CSO.

To ensure resource adequacy, ISO-NE holds a forward capacity auction ("FCA") annually, three years in advance of the relevant capacity delivery year (the Capacity Commitment Period). Resources compete in the FCA to obtain a commitment to supply capacity (a CSO) in exchange for a market-priced capacity payment. Under

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from