FERC Accepts ISO-NE's Inclusion Of Distributed Solar Resources In Calculating Reduced 2019-2020 Capacity Requirement

According to ISO-NE, the inclusion of these distributed solar resources reduced the total load forecast utilized in the ICR.

United StatesEnergy and Natural Resources

On January 8, 2016, the Commission approved proposed values submitted by ISO New England, Inc. ("ISO-NE") to develop a demand curve for the tenth Forward Capacity Auction ("FCA 10"), which is scheduled to be held in February, 2016. One of the values—the Installed Capacity Requirement ("ICR")—for the first time accounted for behind-the-meter solar resources, as a reduction in total load forecast. In its order accepting the proposed demand curve values for FCA 10, the Commission upheld ISO-NE's inclusion of these distributed solar resources in the ICR.

In its November 10, 2015 filing, ISO-NE stated that the Commission, in its order accepting the ICR-related values for FCA 9, directed ISO-NE to explore the incorporation of distributed generation into ISO-NE's ICR calculation in the stakeholder process, and to do so on a schedule that would allow those factors to be reflected in the ICR calculation for FCA 10. ISO-NE stated that the methodology used to calculate the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from