ARTICLE · 22 SEPTEMBER 2011

Federal Energy Regulatory Commission Issues Order No. 1000 – "Transmission Planning And Cost Allocation By Transmission Owning And Operating Public Utilities"

On July 21, 2011, the U.S. Federal Energy Regulatory Commission (FERC) issued Order No. 1000, "Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities," adopting a Final Rule that reforms the "pro forma" Open Access Transmission Tariff (OATT) and the electric transmission planning and cost allocation principles previously adopted in FERC Order 890, "Preventing Undue Discrimination and Preference in Transmission Service."

United StatesEnergy and Natural Resources

On July 21, 2011, the U.S. Federal Energy Regulatory Commission (FERC) issued Order No. 1000, "Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities," adopting a Final Rule that reforms the pro forma Open Access Transmission Tariff (OATT) and the electric transmission planning and cost allocation principles previously adopted in FERC Order 890, "Preventing Undue Discrimination and Preference in Transmission Service."

The reforms set forth in Order No. 1000 apply to new transmission facilities and include the following key reforms:

  • Regional Planning: Public utility transmission providers must participate in a regional planning process through which transmission facilities and non-transmission alternatives may be proposed and evaluated. The process must (1) be included as an attachment to the transmission tariff of the individual transmission provider or the transmission tariff of the Regional Transmission Organization to