EPA Loosens Air Permitting Requirement To Speed Energy And Data Center Construction

On September 9, 2025, EPA announced new guidance on New Source Review (NSR) pre-construction permitting requirements that broadens the types of activities that can be undertaken prior to obtaining an air permit.

United StatesEnergy and Natural Resources

On September 9, 2025, EPA announced new guidance on New Source Review (NSR) pre-construction permitting requirements that broadens the types of activities that can be undertaken prior to obtaining an air permit. The guidance gives permittees flexibility to begin initial construction activities such as pouring pads and constructing building shells—speeding up construction timelines on time-sensitive projects such as semiconductor manufacturers, data centers, and energy projects.

An owner or operator of a facility cannot "begin actual construction" under existing NSR regulations until an air quality permit has been issued; this term is defined as the "initiation of physical on-site construction activities on an emissions unit which are of a permanent nature," including building supports, foundations, and pipework. Consistent with 2020 draft EPA guidance that was never finalized, EPA is revising its interpretation of the term "begin actual construction" to allow for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from