Share on LinkedInShare on LinkedIn

ARTICLE · 29 MARCH 2017

EKPC's Application Requesting FERC Terminate PURPA PPA Requirement Deemed Denied Due To Lack Of Quorum

On March 10, 2017, FERC Secretary Kimberly D. Bose issued a notice that EKPC's application to terminate its requirement pursuant to PURPA to purchase electricity from qualifying facilities was deemed...

United StatesEnergy and Natural Resources

On March 10, 2017, FERC Secretary Kimberly D. Bose ("Secretary Bose") issued a notice that East Kentucky Power Cooperative, Inc.'s ("EKPC") application to terminate its requirement pursuant to the Public Utility Regulatory Policies Act of 1978 ("PURPA") to purchase electricity from qualifying facilities was deemed denied without prejudice due to FERC's lack of quorum (see February 21, 2017 edition of the WER).

On November 7, 2016, as amended on December 7, 2016, EKPC filed an application pursuant to PURPA section 210(m) and section 292.310 of FERC's regulations seeking to terminate the requirement to enter into new power purchase agreements to purchase electricity from qualifying facilities within PJM Interconnection, LLC. In the March 10, 2017 notice, Secretary Bose stated that PURPA sections 210(m)(1) and 210(m)(3), as well as section 292.310 of FERC's regulations, require a final determination by FERC within 90 days as to whether the conditions for termination

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from