ARTICLE · 12 APRIL 2007

"Duking" It Out – What Constitutes Modification Of Facilities Subject To New Source Review

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

On April 2, 2007, the U.S. Supreme Court addressed what constitutes a "modification" at a facility that will trigger new source review (NSR) under the Clean Air Act (CAA). Environmental Defense v. Duke Energy Corp., No.05-848. The decision is "Round One" on the modification question, with the case remanded to the lower court for additional proceedings.

United StatesEnergy and Natural Resources

On April 2, 2007, the U.S. Supreme Court addressed what constitutes a "modification" at a facility that will trigger new source review (NSR) under the Clean Air Act (CAA). Environmental Defense v. Duke Energy Corp., No.05-848. The decision is "Round One" on the modification question, with the case remanded to the lower court for additional proceedings. A final decision will affect all industrial plants subject to NSR and air permitting under prevention of significant deterioration (PSD) regulations.

Under NSR, major modifications – large emission increases resulting from physical changes or changes in the method of operation – at existing facilities require additional emission controls. A modification can include adding or changing a piece of equipment resulting in more emissions.