ARTICLE · 05 NOVEMBER 2020

Department Of Public Utilities Proposes Rethink For Distribution System Planning And Interconnection Costs

On October 22, the Massachusetts DPU issued an Order opening a new docket (DPU 20-75) that seeks comments on a proposal to shake up the way the electric distribution system is planned and...

United StatesEnergy and Natural Resources

On October 22, the Massachusetts DPU issued an Order opening a new docket (DPU 20-75) that seeks comments on a proposal to shake up the way the electric distribution system is planned and paid for in Massachusetts. As I see it, the core idea is to move from being reactive-upgrading the system piecemeal when individual distributed resources seek to interconnect-to being proactive-planning prospectively for the integration of the distributed generation resources we know are coming.

The DPU's proposal would fundamentally change current practice. Currently, in most situations, if an upgrade to the distribution system is needed to interconnect a distributed resource, that distributed resource is responsible for the full cost of the upgrade before it can interconnect, even if the upgrade benefits other customers. This approach is often referred to as "cost causation."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.