Share on LinkedInShare on LinkedIn

ARTICLE · 03 AUGUST 2015

D.C. District Court Judge Chastises The Department Of The Interior, Ordering It To Deliver A Plan On A BLM Drilling Permit, After A 29-Year Suspension

BakerHostetler
BakerHostetler
Contributor
BakerHostetler

BakerHostetler

Recognized as an innovator and one of the top firms for client service, BakerHostetler helps...

View firm profile
Explore more from BakerHostetler

On July 27, 2015, D.C. District Court Judge Richard J. Leon entered a strongly worded order in Solenex LLC v. Jewell.

United StatesEnergy and Natural Resources

On July 27, 2015, D.C. District Court Judge Richard J. Leon entered a strongly worded order in Solenex LLC v. Jewell, chastising the defendants, including the Department of the Interior and numerous other federal agencies, for unreasonably delaying action in their review of Solonex LLC's suspended 1985 drilling permit. Civ. No. 1:13-cv-00993, Doc. No. 52.

The court provided a summary of the "torturous" factual history of the case. Id. at 2. The Bureau of Land Management ("BLM") issued a lease to the plaintiff's predecessor-in-interest in 1982, which covered 6,247 acres in Montana, known as Badger-Two Medicine by the Native American Blackfeet Nation. Subsequently, the BLM approved an application to drill ("APD") a single natural gas exploratory well on January 31, 1985. The BLM then suspended the permit six times, starting October 1, 1985, with the last suspension occurring on July 15, 1998. During this time, "various agencies, including the Forest Service and the BLM

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from