ARTICLE · 11 MAY 2015

D.C. Circuit Upholds FERC Approval Of Gas Compressor Station For Allegheny Storage Project

On April 24, 2015, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied Petitioners' (Citizens of the town of Myersville) review challenging FERC's orders...

United StatesEnergy and Natural Resources

On April 24, 2015, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied Petitioners' (Citizens of the town of Myersville) review challenging FERC's orders approving Dominion Transmission, Inc.'s ("Dominion") "Allegheny Storage Project," and specifically FERC's approval of the construction of a new natural gas compressor station in Myersville, Maryland (the "Myersville Compressor").   In denying the petition, the D.C. Circuit concluded that each of the Petitioners' challenges lacked merit.

The Myersville Compressor is one component of the Allegheny Storage Project, which included the construction of two compressor stations and an additional pipeline that would, among other things, provide Dominion customers an additional 115,000 dekatherms per day of firm transportation in Maryland, Ohio, West Virginia, and Pennsylvania.  Previously, FERC conditionally approved the Allegheny Storage Project in December of 2012; the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from