ARTICLE · 30 JUNE 2014

D.C. Circuit Rules That FERC May Not Segment Its Evaluation Of The Environmental Impact Of Related Natural Gas Pipeline Construction Projects, Regardless Of Whether They Are Separately Proposed

The D.C. Circuit Court of Appeals recently issued an opinion holding that the FERC violated the National Environmental Policy Act.

United StatesEnergy and Natural Resources

The D.C. Circuit Court of Appeals recently issued an opinion holding that the Federal Energy Regulatory Commission (FERC) violated the National Environmental Policy Act (NEPA) when it segmented its evaluation of the environmental impact of four separately proposed but connected projects to upgrade the "300 Line" on the Eastern Leg of Tennessee Gas Pipeline Company's natural gas pipeline system.  Going forward, the court's ruling will likely compel proponents of interrelated or complimentary pipeline projects to seek their certification on a consolidated basis and will require FERC to evaluate their cumulative impact.

Tennessee Gas's challenged Northeast Project was the third of four proposed upgrade projects to expand capacity on the existing Eastern Leg of the 300 Line.  The Northeast Project added only 40 miles of pipeline, while the four proposed projects combined to add approximately 200 miles of looped pipeline.  FERC approved Tennessee Gas's first proposed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.