D.C. Circuit Rejects Seminole Electric Cooperative's Appeal For Additional Refunds

On June 30, 2017, the United States Court of Appeals for the D.C. Circuit denied a petition by Seminole Electric Cooperative, Inc. seeking to increase the refund amount FERC ordered FP&L...

United StatesEnergy and Natural Resources

On June 30, 2017, the United States Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied a petition by Seminole Electric Cooperative, Inc. ("Seminole") seeking to increase the refund amount FERC ordered Florida Power & Light Company ("FP&L") to pay Seminole for overcharges related to energy imbalance services. Seminole raised two challenges to FERC's refund order: (1) FERC improperly restricted the refund period to twenty-four months, as opposed to the full four and a half year period for which FP&L overcharged Seminole for energy imbalance services; and (2) FERC failed to require that energy imbalance charges be apportioned among the three tiers established in Schedule 4 of FP&L's Tariff.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from