D.C. Circuit Rejects FERC's Use Of FPA Section 205 To Revise PJM Minimum Offer Price Rule

On July 7, 2017, the U.S. Court of Appeals for the D.C. Circuit ("D.C. Circuit") vacated and remanded a set of FERC orders that revised the minimum offer price rule ("MOPR") of PJM Interconnection, L.L.C. ("PJM").

United StatesEnergy and Natural Resources

On July 7, 2017, the U.S. Court of Appeals for the D.C. Circuit ("D.C. Circuit") vacated and remanded a set of FERC orders that revised the minimum offer price rule ("MOPR") of PJM Interconnection, L.L.C. ("PJM").  The D.C. Circuit held that FERC exceeded its role under Federal Power Act ("FPA") Section 205 by imposing changes that amounted to an "entirely new rate scheme" for PJM.

In July 2012, an ad hoc group of PJM generators began discussing potential reforms to PJM's MOPR—a rule designed to curb the ability of new generators to artificially depress capacity auction clearing prices by submitting below-cost bids.  The reform efforts focused on various features of the MOPR, including "unit-specific review," which at the time allowed PJM to exempt certain generators from the MOPR if they could demonstrate that their actual costs were below the floor.  Arguing that unit-specific review lacked sufficient transparency and depressed capacity market clearing prices

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from