ARTICLE · 10 DECEMBER 2015

D.C. Circuit Rejects FERC's Interpretation Of Municipal Preference In Permitting Of Hydroelectric Projects

The D.C. Circuit relied on the plain meaning of the statute in holding that Section 7(a) unambiguously requires FERC to grant the municipal preference to Western Minnesota's application.

United StatesEnergy and Natural Resources

On November 20, 2015, the United States Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") rejected the Federal Energy Regulatory Commission's ("FERC") holding that Federal Power Act ("FPA") Section 7(a) limits the municipal preference in original licensing for hydroelectric projects to municipalities located in the vicinity of the water resource to be developed. The D.C. Circuit case, Western Municipal Power Agency v. FERC, No. 14-1153 (issued Nov. 20, 2015), was filed on appeal of FERC orders refusing to grant a municipal preference to Western Minnesota. The D.C. Circuit granted Western Minnesota Municipal Power Agency's ("Western Minnesota") petition for review, vacated the Commission's underlying orders, and remanded the proceeding to FERC.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from