DC Circuit Re-Affirms Its "Broad View" Of A Small Power Production Facility's "Power Production Capacity" After Loper Bright Remand

Steptoe LLP
Steptoe LLP
Contributor
Steptoe LLP

Steptoe LLP

Steptoe International (UK) LLP has built a strong reputation for providing top-quality regulatory,...

View firm profile
Explore more from Steptoe LLP

Disagreement over whether the Broadview Solar facility should or should not be a QF has now lasted over five years and has been the subject of many past blog posts.

United StatesEnergy and Natural Resources

Disagreement over whether the Broadview Solar facility should or should not be a QF has now lasted over five years and has been the subject of many past blog posts. The DC Circuit has now issued its second opinion on the topic, but it remains to be seen if the 2-1 opinion will be the final word. In SEIA v. FERC, a majority of the D.C. Circuit panel one again upheld FERC's decision to classify the solar facility's "power production capacity" under PURPA as the "amount of electric power that is transmitted from the facility to the grid for customer use—its 'send out.'" The court explained: "In the simplest terms, the net output equals the amount of electric power that is transmitted from the facility to the grid for customer use—its 'send out.'" The decision follows a remand from the Supreme Court under Loper Bright, which directed the D.C. Circuit to re-evaluate the case without applying Chevron deference.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from