DC Circuit Grants Emergency Stay For Proposed Powerplant

Jenner & Block LLP
Jenner & Block LLP
Contributor
Jenner & Block LLP

Jenner & Block LLP

Jenner & Block’s London office has built a powerful reputation for representing clients in their...

View firm profile
Explore more from Jenner & Block LLP

A firm team represents NTE Connecticut, LLC, which for several years has been developing a large powerplant that will connect to the New England electric grid, ...

United StatesEnergy and Natural Resources

A firm team represents NTE Connecticut, LLC, which for several years has been developing a large powerplant that will connect to the New England electric grid, bringing reliable, cleaner power to the region that will help facilitate the integration of offshore wind and other renewable energy. But because of lengthy litigation brought in an ultimately unsuccessful attempt to vacate its environmental permits, and other factors like navigating through the pandemic, NTE has been delayed in starting construction.

Last November, the regional grid operator, ISO New England Inc., submitted a request to the Federal Energy Regulatory Commission (FERC) to terminate a key source of income for NTE – its capacity supply obligation contract. Under this contract, NTE (and other generators) promise to provide electricity to the grid in future years at a rate determined in annual auctions. ISO New England claimed that termination was warranted because, in its view, NTE would not meet

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from