ARTICLE · 14 MARCH 2018

D.C. Circuit Defers To FERC's Qualitative Approach For Establishing Term For Hydroelectric Project Licenses

On March 6, 2018, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied Duke Energy Carolinas, LLC's ("Duke Energy") petition for review of FERC's grant of a forty-year license...

United StatesEnergy and Natural Resources

On March 6, 2018, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied Duke Energy Carolinas, LLC's ("Duke Energy") petition for review of FERC's grant of a forty-year license for the Catawba-Wateree Project ("Project").  FERC had found that, despite Duke Energy's requested fifty-year term for the license renewal, the measures required by FERC in issuing the license were only "moderate," and thus warranted the forty-year term.  Duke Energy argued that FERC acted arbitrarily and capriciously by not granting the fifty-year license.  The D.C. Circuit deferred to FERC's analysis in granting a forty-year license.

Duke Energy's original license had been for a fifty-year term.  Prior to the expiration of that license, Duke Energy filed an application for a new license with another fifty-year term.  During the application process, Duke Energy entered into a relicensing agreement with seventy entities, which required Duke Energy to satisfy

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from