D.C. Circuit Court Of Appeals Upholds FERC’s Approval Of Interstate And Intrastate Pooling Cost Arrangement For Trans Alaska Pipeline

The U.S. Court of Appeals for the D.C. Circuit held that FERC had the authority to approve a cost pooling agreement among the carriers of the Trans Alaska Pipeline System...

United StatesEnergy and Natural Resources

On February 20, 2015, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") held that FERC had the authority to approve a cost pooling agreement among the carriers of the Trans Alaska Pipeline System ("TAPS") that allocates certain fixed costs on the basis of each carrier's share of combined interstate and intrastate utilization of TAPS.  In upholding this determination by FERC, the D.C. Circuit found that FERC could indirectly regulate intrastate oil prices as a result of its regulation of interstate prices.

Three carriers have a joint interest in TAPS.  Each carrier's percentage of capacity on TAPS is operated by the carriers' joint agent, Alyeska Pipeline Service Company.  The service offered by each carrier is identical, and either interstate or intrastate transportation can be achieved through any of the three carriers' offerings.  The original rates for shipping oil on TAPS were highly contested and subject to protracted litigation. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from