D.C. Circuit Affirms FERC Refund Denial In Louisiana PSC Cost Allocation Challenge

As the court summarized, in the absence of utility over-recovery, FERC is generally reluctant to order refunds in cases involving flawed rate design for two reasons.

United StatesEnergy and Natural Resources

In a decision issued on March 6, 2018, the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit" or the court) upheld a series of FERC orders declining to direct Entergy Services Inc. ("Entergy") to pay refunds for previously misallocated capacity costs. The D.C. Circuit found that FERC adequately explained its reasoning and clarified that—contrary to previous assertions—the Commission has no general policy of ordering refunds in cases involving flawed rate design, and that it had adequately explained that such a refund order would be inequitable in this instance.

The origins of this long-running dispute date back to a multi-state system agreement in which Entergy, and several other Entergy Company-branded public utilities, are members and share certain costs, such as for capacity. In the mid-1990s, the Louisiana Public Service Commission ("LAPSC") filed a Federal Power Act ("FPA") Section 206 complaint at FERC arguing against Entergy's inclusion

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.