On July 24, 2018, the U.S. Court of Appeals for the D.C. Circuit ("D.C. Circuit") affirmed FERC's 2015 and 2016 orders denying challenges to ISO New England's ("ISO-NE")...

United StatesEnergy and Natural Resources

On July 24, 2018, the U.S. Court of Appeals for the D.C. Circuit ("D.C. Circuit") affirmed FERC's 2015 and 2016 orders denying challenges to ISO New England's ("ISO-NE") ninth and tenth Forward Capacity Auctions ("FCA 9" and "FCA 10") and approving the results of those auctions. The D.C. Circuit found that petitioners, Utility Workers Union of America Local 464 and its President, Robert Clark, failed to establish standing to challenge the FERC orders approving the results of FCA 9 and FCA 10.

Shortly before ISO-NE's eighth FCA ("FCA 8"), in February 2014, the owners of the Brayton Point Power Station ("Brayton Point"), a coal-fired electric generating unit in Somerset, Massachusetts, announced the plant's retirement. Because the plant's owners announced the retirement after the deadline for other wholesale electricity suppliers to participate in FCA 8, petitioners challenged the plant's closure before FERC, contending that the restricted supply caused by the plant's

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from