On March 16, 2018, the U.S. Court of Appeals for the District of
Columbia Circuit ("D.C. Circuit") affirmed FERC's (1)
reduction in NorthWestern Corporation's
("NorthWestern") Schedule 3 regulation service rate by
removing "regulation-down" capacity from the rate's
numerator and increasing the denominator to the full nameplate
capacity of NorthWestern's generating facility and (2) decision
to order NorthWestern to refund customers the difference between
NorthWestern's proposed rate and FERC's approved rate.
Prior to 2011, NorthWestern lacked the generating capacity to
self-supply regulation service –generation that maintains the
frequency of the transmission system by responding to variations in
demand for electricity in real time. Instead, NorthWestern
purchased regulation service from third parties and passed on the
costs of these purchases to its customers. However, after
constructing a new generating facility in 2011, NorthWestern filed
revisions to its