Client Alert: FERC Issues Final Rule On How To Plan And Pay For Electricity Transmission

Jenner & Block LLP
Jenner & Block LLP
Contributor
Jenner & Block LLP

Jenner & Block LLP

Jenner & Block’s London office has built a powerful reputation for representing clients in their...

View firm profile
Explore more from Jenner & Block LLP

On May 13, 2024, the Federal Energy Regulatory Commission (FERC) issued its long-awaited final rule on regional transmission planning and cost allocation...

United StatesEnergy and Natural Resources

On May 13, 2024, the Federal Energy Regulatory Commission (FERC) issued its long-awaited final rule on regional transmission planning and cost allocation, Order No. 1920. The final rule's release follows a notice-and-comment period that drew over 600 comments from interested parties, amounting to over 30,000 pages from nearly 200 stakeholders—the largest record considered in any FERC proceeding, according to FERC staff.1

The rule is a hefty 1,300 pages, so this alert highlights select issues of particular importance to market participants and notes the flashpoints of disagreements amongst the commissioners.

Long-Term Regional Transmission Planning

The final rule establishes a long-term planning horizon timeline of 20 years. Transmission providers must conduct this planning at least every five years. This longer planning horizon would be required of all RTOs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from