Historically, transmission infrastructure has been built to link
electricity generation with demand centers. Accordingly, it has
been common to levy transmission infrastructure charges on
customers' peak demand, which has tended to drive these costs.
However, the drivers of transmission costs are changing. Large
scale integration of utility scale renewables requires significant
investment in transmission infrastructure. With rising costs,
designers of network tariffs now face the challenge of recovering
these new costs through transmission infrastructure tariffs, which
should also send price signals encouraging the efficient use and
development of the grid.
In this white paper, Senior Managing Director Richard Druce and
Senior Consultant/ Principal Michael Dawes note that transmission
costs associated with integrating renewables are not driven by the
need to meet peaks in demand, so using peak demand charges (or
standing charges) to recover costs may not be cost