Appeals Court Validates FERC Regional Planning Mandate As Reasoned Evolution Of The Open-Access Electricity Transmission System

The Federal Energy Regulatory Commission’s Order No. 1000 mandate that going forward the high-voltage electric transmission grid be planned and fairly financed regionally by all of its operators and beneficiaries, survived myriad challenges from 45 petitioners in the unanimous August 15 decision of a three-judge panel of the U.S. Court of Appeals for the D.C. Circuit in South Carolina Public Service Authority v. FERC.

United StatesEnergy and Natural Resources

The Federal Energy Regulatory Commission's (FERC) Order No. 1000 mandate that going forward the high-voltage electric transmission grid be planned and fairly financed regionally by all of its operators and beneficiaries, survived myriad challenges from 45 petitioners in the unanimous August 15 decision of a three-judge panel of the U.S. Court of Appeals for the D.C. Circuit in South Carolina Public Service Authority v. FERC.  The rigorous 97-page opinion rejected challenges coming from all directions to the 2011 rulemaking entitled "Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities."

According to the panel, nearly all of the challenges misapprehended Order No. 1000's regional planning mandate.  The court repeatedly emphasized that Order No. 1000's mandate is nothing new, but rather the next step in evolving efforts under section 206 of the Federal Power Act to combat undue discrimination.  That evolution, the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from