Share on LinkedInShare on LinkedIn

ARTICLE · 02 DECEMBER 2022

Another Legal Victory For New England Clean Energy Connect But, Unbelievably, It Still Isn't Nearly Out Of The Woods

Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.
Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.
Contributor
Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

Mintz is a litigation powerhouse and business accelerator serving leaders in life sciences, private...

View firm profile
Explore more from Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

Yesterday Maine's Supreme Judicial Court unanimously held that the 2021 referendum that purported to invalidate a lease essential to the New England Clean Energy Connect project violated...

United StatesEnergy and Natural Resources

Yesterday Maine's Supreme Judicial Court unanimously held that the 2021 referendum that purported to invalidate a lease essential to the New England Clean Energy Connect project violated the Contract Clause of the United States Constitution.  In the 2021 referendum one in four registered Maine voters determined that the Project should not proceed after hundreds of millions of dollars had already been invested with the approval of the Federal and State Governments.

As a result of Maine's highest court's decision yesterday, the Maine Bureau of Parks and Lands lease of 2.6 percent of the Johnson Mountain and West Forks Plantation "public reserved lands" for the Project remains undisturbed.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from