Share on LinkedInShare on LinkedIn

ARTICLE · 13 MAY 2006

ALJ Issues Initial Decision on Gas Quality and Interchangeability Standards for LNG Imports to Florida

On April 11, 2006, Federal Energy Regulatory Commission ("FERC" or the "Commission") Administrative Law Judge Herbert Grossman ("ALJ") issued an initial decision in the AES v. FGT proceeding.

United StatesEnergy and Natural Resources

Originally published April 21, 2006

On April 11, 2006, Federal Energy Regulatory Commission ("FERC" or the "Commission") Administrative Law Judge Herbert Grossman ("ALJ") issued an initial decision in the AES v. FGT proceeding. The proceeding, the first fully litigated case before FERC involving gas composition issues related to imports of liquefied natural gas ("LNG"), determined the appropriate natural gas quality and interchangeability standards for re-gasified LNG introduced into the Florida Gas Transmission Company ("FGT") pipeline system. The ALJ adopted standards that seek to encourage natural gas supply, while at the same time protect the pipeline’s physical integrity and assets connected to the system.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from