ARTICLE · 07 OCTOBER 2013

Tribunal Considers Issues Of Cargo Quantity, Responsibility For Broken Cargo Equipment, Demurrage And The Margin Of Redelivery Bunkers Allowed By The Term "About"

The Claimants chartered the Vessel to the Respondents on an amended NYPE form.

United KingdomTransport

London Arbitration 15/13

The Claimants chartered the Vessel to the Respondents on an amended NYPE form. The Respondents agreed a sub-voyage charter for the carriage of 50,000mt corn in bulk, 10% more or less in the Respondents' option, from Brazil to Indonesia.

In arbitration proceedings between the parties, four key issues were decided:

  1. Were the Claimants in breach due to the Master's failure to properly sign accurate mate's receipts in respect of cargo loaded?
  2. Were the Respondents liable for the cost of replacing a damaged hoisting wire?
  3. Were the Claimants in breach due to the Master's failure to protest the Statement of Facts at the second discharge port, reducing the amount of demurrage which the Respondents could claim under the sub-charter?